Post by genie on Feb 12, 2014 14:28:29 GMT 12
12th Feb. 2014 replaced lures on Bridge Track. One rat in box 15. August 16th 2014 new lures and poison in place. August 28th 2014 Boxes checked poison replaced as required. December 6th 2014 lures changed traps checked. 2015 Jan 30th. Boxes checked new lures. Poison placed in rat cafes. March 6th 2015. Lures placed in all boxes. April 10th boxes checked.
|
|
|
Post by genie on Mar 16, 2014 5:52:47 GMT 12
The Bridge Track has been set up for the Willis Project, bait stations or rat cafes, tracking tunnels etc. On March 14th cards were placed in tunnels, pre feed in rat cafes or Philproofs and boxes closed down. To date only ant prints have been found on the cards pluc many of the ants themselves. The camera showed two different cats.
|
|
|
Post by genie on Mar 19, 2014 8:47:11 GMT 12
March 19th. First rat print on tracking card on Willis Project Bridge Line. Numerous ants, tiny ants busy eating the peanut butter and a few mice prints appearing now. It could take some weeks to pull rats up from their hidden places so the first rat print is encouraging.
|
|
|
Post by genie on Apr 14, 2014 7:22:23 GMT 12
12th April 2014 all lures replaced. Two boxes and a Timms on side track to fence.
|
|
|
Post by genie on Jun 23, 2014 19:12:51 GMT 12
Walked her Bridge track as far as the extension to the fence line. re set two Timms with fish heads and new lures in boxes 6a and 6B.
|
|